Friday, January 13, 2012

Progress Update

Germantown Emergency Notification
The ENS implementation continues. Some GT buildings have the ENS in them.
Connection from the ENS to the infrastructure is still being planned.
Walkthrough for patch cables was done Dec 15th.
A meeting is scheduled for January 13th to review patch amount and other questions concerning the IDF’s.

Thursday, October 13, 2011

Progress Update

Germantown Activities
Germantown Emergency Notification
The ENS device I planned to be on the wall where ever possible.
The mockup design has been reviewed by facilities.
SA building is still on schedule for completion

Tuesday, October 4, 2011

Progress Update

Germantown Activities
HT renovation 103 can be closed
HS renovation of room 216,205,203,236, and 238 - An E-mail was sent to all team members that since there were action items remaining on this project it could be closed.
Germantown Emergency Notification
The contractor continues to work in the SA building preparing paths for the cabling.
There is going to be a mockup design for facilities to review.

Thursday, September 1, 2011

Progress Update

Germantown Activities
• HT 103 – Project Completed.
Germantown Emergency Notification
• At this point there are no outstanding issues.

Friday, August 5, 2011

Progress Update

Germantown Activities
Refer to HS room renovation project.
SA 103 – Cabling vendor is waiting for PO from the college.
Germantown Emergency Notification
Attended the Pre-construction meeting in the Goldenrod Building on the Germantown Campus to review scope of work in SA for the ENS project.
Reviewed scope of work, rules for vendor on site, coordination with facilities and security, timeline.

Tuesday, July 26, 2011

Progress Update

Refer to HS room renovation project.
HT 103 to be renovated. Site meeting setup for July 21st.
Germantown Emergency Notification
• Facilities have received a estimated work schedule on implementing the equipment.



Germantown HS room renovation 216, 203, 205, 236,and 238
• Room 203 is being used for classes.
• The desk hangers are still on order for room 203.
• The new PC’s are still on order for room 203.
• A progress meeting will be setup to follow up on any other outstanding issues

Monday, July 11, 2011

Progress Update

Reviewed the emergency notification schedule from the vendor.
Room 203 is being used for classes.
The desk hangers are still on order for room 203.
A table has been placed in the room 203 for a printer.
The new PC’s are still on order for room 203.
A progress meeting will be setup to follow up on any other outstanding issues.