Tuesday, January 20, 2009

Progress Update

The SA building is having the security department, mail room, and old facilities location renovated. This will be done three phases.

Meeting to discuss more details of renovation. (1/22/09)

First phase of the renovation for old facilities location is to start the second week of Feburary. The college cabling can be removed before existing cabling anytime prior to the second week of February. The estimated time for the college cabling group to remove the old cabling is January 14th, 2009.

A meeting to review the status of the renovation is scheduled for January 13, 2009.

The next phase to do renovation is the security area. This timeline has not been establised. The completion of the first phase will determine the timeline of the next phase.

The final phase will be the mail room on the first floor to be renovated.