· Data and Voice cable completed at the edge.
· One client has moved to there new location
· Facilities – To create a client to and from list
· When the sprinkler system is completed a move date will be coordinated.
· The voice group needs to cross connects for the recording line on the same day of the move.
· Facilities - will handle the coordination of the base security station moving
· Cabling group- to send IT PM the work order number for the work being performed by the cabling group.
· The next meeting will be TBA
· Working with vendor and the NE group for wireless quote.
Monday, March 16, 2009
Thursday, March 5, 2009
Project Update
The facilities group has started renovating the SA locations with mechanical, electric, and painting.The cabling group has started pulling new data and voice cable to the locations.
The client move has not been determined at this time. The other phases of this renovation as not been specified has of this time.
The client move has not been determined at this time. The other phases of this renovation as not been specified has of this time.