Thursday, April 30, 2009

Status Update

April 20th – May 8th Mailroom move Mid May

The college cabling group has started pulling cables in the renovated area of the old security location.

May 1st is an IT team update meeting.

On Monday, May 4th, a meeting is setup with client to discuss the back-fill work for the mail room.

Thursday, April 16, 2009

Progress update

Security group moved into new location.

Demo of Old Security Pantry / Base Station / Locker Rooms: April 2 – 6th Asbestos abatement: April 7 – 14th New Construction: April 20th – May 8th Mailroom move Mid May

Security area for client and base station complete. The next phase of the old security area is being worked on.

Thursday, April 2, 2009

Progress Update

The security group was moved on April 1st. The weather station (PC) will need the cable dropped in the wall.
The move went well.
The next phase below has started.

Demo of Old Security Pantry / Base Station / Locker Rooms: April 2 – 6th Asbestos abatement: April 7 – 14th New Construction: April 20th – May 8th Mailroom move Mid May