·The infrastructure installed in the telecomm closet has been tested.
·The project is being moved forward with an anticipated completion by the end of January 2010.
Site visits.
·College cabling has removed existing cabling from the renovated area.
·Working with infrastructure has to when the AP’s can be installed.
Wednesday, December 23, 2009
Progress Update
Communicating with facilities and other IT groups activities that may need the assistance of the FIP group.
No addtional information at this time.
No addtional information at this time.
Thursday, December 10, 2009
Progress Update
Germantown campus trailer removal:
The trailer has been removed from the campus.
Communicating with facilities and other IT groups for any activities that may need the assistance of the FIP group.
The trailer has been removed from the campus.
Communicating with facilities and other IT groups for any activities that may need the assistance of the FIP group.
Subscribe to:
Posts (Atom)