Germantown Activities:
Per T-mobile they have completed their work on Germantown campus.
Developmental Math Rooms:
A walkthrough of the three rooms have been completed on gathering IT information to be given to the project leader. No specific dates have been determined.
Blog Archive
Thursday, December 9, 2010
Thursday, November 4, 2010
Progress Update
T-mobile is preparing to program their equipment. This should be no impact to campus daily functions.
HS Room 175 RenovationFacilities are working with the client since power in the building is a concern when adding additional peripherals to expand classrooms.
Following up on T-mobile activities their final programming of the equipment. This should be no impact to campus daily functions.
Continue working on supporting documentation for HS room 175.
Follow up with facilities on their planned activities for HS room 175.
HS Room 175 RenovationFacilities are working with the client since power in the building is a concern when adding additional peripherals to expand classrooms.
Following up on T-mobile activities their final programming of the equipment. This should be no impact to campus daily functions.
Continue working on supporting documentation for HS room 175.
Follow up with facilities on their planned activities for HS room 175.
Friday, October 15, 2010
Progress Update
T-mobile has completed their trenching for new cable for their equipment. This is being monitored by IT and facilities.
HS Room 175 Renovation
The HS building in planning to have room 175 renovated. WDCE will be the client.
Created project plan, Specifications, communication plan, issue log, Gantt chart, Mariner created project, organization chart.
Facilities are working with the client since power in the building is a concern when adding additional peripherals to expand classrooms.
Following up on T-mobile activities for their cable implementation.
Continue working on supporting documentation for HS room 175.
Follow up with facilities on their planned activities for HS room 175.
HS Room 175 Renovation
The HS building in planning to have room 175 renovated. WDCE will be the client.
Created project plan, Specifications, communication plan, issue log, Gantt chart, Mariner created project, organization chart.
Facilities are working with the client since power in the building is a concern when adding additional peripherals to expand classrooms.
Following up on T-mobile activities for their cable implementation.
Continue working on supporting documentation for HS room 175.
Follow up with facilities on their planned activities for HS room 175.
Friday, October 1, 2010
Progress Update
T-mobile has completed their trenching for new cable for their equipment. This is being monitored by IT and facilities.
Following up on T-mobile activities for their cable implementation.
Following up on T-mobile activities for their cable implementation.
Wednesday, August 18, 2010
Progress Update
Working on creating documents for the implementation of this project.
The HS building in planning to have room 175 renovated. WDCE will be the client.
T-mobile has not started on their trenching a new cable for their equipment
Follow up with co-worker on more detail about the HS room 175 renovations.
Follow up with facilities on where T-mobile is on their work.
Preparing future meetings for IT team members.
The HS building in planning to have room 175 renovated. WDCE will be the client.
T-mobile has not started on their trenching a new cable for their equipment
Follow up with co-worker on more detail about the HS room 175 renovations.
Follow up with facilities on where T-mobile is on their work.
Preparing future meetings for IT team members.
Thursday, August 5, 2010
Progress Update
The facilities group is working with T-mobile on start date for trenching.
T-mobile has not started trenching because the easment where the trenching will take place belongs to Montgomery County.
Some water trenching was being done near the water tower for preparation of phase I of the GT BE project.
T-mobile has not started trenching because the easment where the trenching will take place belongs to Montgomery County.
Some water trenching was being done near the water tower for preparation of phase I of the GT BE project.
Thursday, June 10, 2010
Progress Update
T-mobile T-1 lines are planned to be updated which means there will be trenching performed on the campus.
A work order has been placed to the cabling group to monitor the work to be performed.
Facilities are working to setup a walkthrough with the vendor and college cabling group to work out any concerns about the trenching.
The question has been asked whether or not Miss Utility has been on campus to mark the trenching area.
Follow up on when the walkthrough will take place.
Follow up if Miss Utility been notified and the work area marked.
Follow up with GT facilities on a planned meeting with the contractor.
A work order has been placed to the cabling group to monitor the work to be performed.
Facilities are working to setup a walkthrough with the vendor and college cabling group to work out any concerns about the trenching.
The question has been asked whether or not Miss Utility has been on campus to mark the trenching area.
Follow up on when the walkthrough will take place.
Follow up if Miss Utility been notified and the work area marked.
Follow up with GT facilities on a planned meeting with the contractor.
Thursday, June 3, 2010
Progress Update
The client move is scheduled for May 28th. The move has been completed. I will follow up with IT team and facilites.
Confirmed with infrastructure team that all connectivity is working out to the edge.
Walk through on day of client move.
Work on Lesson Learned with project team
Confirmed with infrastructure team that all connectivity is working out to the edge.
Walk through on day of client move.
Work on Lesson Learned with project team
Thursday, May 13, 2010
Progress Update
An estimated client move in dates is May 28th – June 1st.
Received infrastructure sign-off for the SOW.
Site visits to location of project.
Coordination meeting with facilities and IT groups is setup for May 21st.
Follow up on infrastructure scope of work to be signed off.
Follow up that IT projects and Asset management are available for the client move.
Received infrastructure sign-off for the SOW.
Site visits to location of project.
Coordination meeting with facilities and IT groups is setup for May 21st.
Follow up on infrastructure scope of work to be signed off.
Follow up that IT projects and Asset management are available for the client move.
Progress Update
There are no additional activities the FIP group is aware of. I will continue to monitor and communicate with facilities for any GT activities related to IT.
Friday, April 30, 2010
Progress Update
There are no additional activities the FIP group is aware of. I will continue to monitor and communicate with facilities for any GT activities related to IT.
I continue communicating with facilities for any additional work being performed at the campus that would need its assistance.
I continue communicating with facilities for any additional work being performed at the campus that would need its assistance.
Friday, April 16, 2010
Progress Update
Based on the facilities meeting a few weeks ago their work load will be slowed down to concentrate on closing out other projects. There are no additional activities the FIP group is aware of.
I continue communicating with facilities for any additional work being performed at the campus that would need IT’s assistance.
I continue communicating with facilities for any additional work being performed at the campus that would need IT’s assistance.
Thursday, April 1, 2010
Progress update
I plan to continue communicating with facilities every week either by getting information from their weekly Monday facilities meeting or E-mailing the Germantown PM.
Monday, March 8, 2010
Progress Update
At this time there are no IT activities with the GT campus. I will continue to check with facilities and monitor the campus with site visits.
Friday, February 19, 2010
Progress update
Communicate with facilities and other IT group activities that may need the assistance of the FIP group.
Monitoring any possible IT related activities that may involve IT departments.
Monitoring any possible IT related activities that may involve IT departments.
Wednesday, February 10, 2010
Progress Update
The build-out of the renovated are has started.
A meeting has been rescheduled for late February to review project activities.
A meeting has been rescheduled for late February to review project activities.
Progress Update
Communicate with facilities and other IT group activities that may need the assistance of the FIP group.
Thursday, January 21, 2010
Progress Update
Communicate with facilities and other IT group activities that may need the assistance of the FIP group.