Friday, February 18, 2011

Progress Update

Attended the Science Applied programming session on January 12th
Humanities building will have room 216, 203,205, 236, and 238 renovated this spring semester. Cabling vendor to come on site today for a walkthrough.
Room 216 renovation started Feb. 8th. Existing data and voice cabling was used for the new locations.
Work orders will be used for the IT groups to perform their duties on this project.
Workstation and SIWS cost has been sent to Mike Russell for review. Still not sure who will be paying for these items.
Working with facilities on how this project will be funded.
Received a cabling quote from the vendor.