Wednesday, March 30, 2011

Progress Update

HS building room 203 and 205 has started cabling for the room. Partial cabling will be done since it will be needed for classes while rooms 236 and 238 are being renovated.
Site walkthrough scheduled on March 11th.
Progress meeting scheduled for March 25th.
The PO for the cabling material has been sent to the cabling contractor.
HS room 236 and 238 are estimated to start renovation March 28th.
Cabling is estimated to start in room 236 and 238 April 19th.
Removal of workstations in room 236 was scheduled for March 24.