Thursday, April 28, 2011

Progress Update

Setup walkthrough dates for fiber location into each building and IDF layout for the fiber project.
The furniture has been placed in room 236 and 238.
The workstations were relocated into room 236.
A site walkthrough is scheduled for April 29th.
The SIWS are still on order for some of the rooms.
Room 216 is being used as storage for now.
Room 203 is waiting for workstation furniture and once the furniture is installed the cabling can be completed.

Thursday, April 21, 2011

Progress Activities

The data cabling in room HS 236 and 238 have completed.
The connections into the IDF is being worked on by the infrastructure team.
The flooring is still being worked on by facilities.
The computers are scheduled to be placed into room 236 for Thursday April 28th.
The room are estimated to be ready on May 2nd for classes.