Thursday, April 21, 2011

Progress Activities

The data cabling in room HS 236 and 238 have completed.
The connections into the IDF is being worked on by the infrastructure team.
The flooring is still being worked on by facilities.
The computers are scheduled to be placed into room 236 for Thursday April 28th.
The room are estimated to be ready on May 2nd for classes.