Thursday, June 23, 2011

Progress Update

Reviewed emergency notification scope of work with IT infrastructure group. There are still a lot of unanswered questions about the project.
Facilities are waiting for the contractors SOW and timeline to review and discuss more details about the project.

Data connectivity for room 203 was completed on June 17th.
The request to move the PC from storage back to room 203 has been completed.
The work desk will need hangers to hold the PC’s. Facilities will order the hangers.
A progress meeting will be setup to follow up on any other outstanding issues.