HS building room 203 and 205 has started cabling for the room. Partial cabling will be done since it will be needed for classes while rooms 236 and 238 are being renovated.
Site walkthrough scheduled on March 11th.
Progress meeting scheduled for March 25th.
The PO for the cabling material has been sent to the cabling contractor.
HS room 236 and 238 are estimated to start renovation March 28th.
Cabling is estimated to start in room 236 and 238 April 19th.
Removal of workstations in room 236 was scheduled for March 24.
Wednesday, March 30, 2011
Thursday, March 3, 2011
Progress Update
Humanities building room 216 has been completed its renovation. The Media resources group is working to replace the old SIWS.
HS building room 203 and 205 renovation work has started.
Progress meeting was held on Feb 18th and Feb 25th.
IT will be funding for new SIWS and PC replacement.
Sent cabling quote to the facilities to process and facilities has sent it to procurement.
HS building room 203 and 205 renovation work has started.
Progress meeting was held on Feb 18th and Feb 25th.
IT will be funding for new SIWS and PC replacement.
Sent cabling quote to the facilities to process and facilities has sent it to procurement.